Custom medals arranged on a production timeline calendar, showing sample and production stages

You’ve found a factory, picked a design direction, and now you need to know two things: how many medals do you have to order, and how long will it take? Get those numbers wrong and your medals either arrive after the ceremony or you’re left with a warehouse full of surplus stock.

This guide covers both questions in plain terms—minimum order quantities, what the lead time clock actually measures, and how to work backwards from your event date to your deposit deadline.

Minimum order quantity: 100 medals per design

The MOQ at Gumei Medals is 100 pieces per design. That figure is set by tooling economics: each design needs its own metal mould, and running a stamping or die-casting machine for fewer than 100 pieces doesn’t recover the setup cost.

A few points that often cause confusion:

Situation How MOQ works
Multiple designs, same event Each design counts separately — 3 designs = 300 medals minimum (100 per design)
Gold, silver and bronze One design, three plating colours = still 100 total (not 100 each)
Repeat order, same mould The mould fee is waived; the MOQ still applies
Virtual or tiered events Each medal variant with a unique shape = its own design and its own 100-piece minimum

If you need three sizes of medal for one championship—podium, participant and volunteer—you need three designs and at least 300 medals total. If the podium and participant medals share the same die but differ only in plating, they count as one design.

One-off costs before the per-unit price

Before the unit price, every new design carries two one-off fees:

  • Design fee: USD 100 — covers your colour draft and the production vector artwork. If you go ahead with the order, it is credited against your invoice.
  • Mould fee: USD 420 — a one-off charge to engrave the metal die. We keep the mould on file, so repeat orders are mould-free.

These fees don’t scale with quantity, which is why larger runs cost proportionally less per piece.

Lead time: what the clock measures and when it starts

The full journey from first enquiry to medals in your hands has two sequential stages.

Stage 1 — Sample: 7 days

The sample clock starts when you approve the final artwork. We produce one physical sample and ship it to you. Sample lead time covers making the first piece from your mould; it does not include transit time to your address.

Stage 2 — Production: 7 days (included in the 14-day total)

The production clock starts when you approve the physical sample. Full production, finishing and packaging take roughly 7 more days, giving a combined 14-day factory lead time from artwork approval to cargo-ready.

Adding transit time:

Shipping method Typical transit time Total from artwork approval
DDP by air 5–7 days ~21 days
DDP by sea 25–35 days ~49 days
CIF Depends on destination ~49+ days
EXW Pick up at factory ~14 days to gate

Lead time starts from artwork approval, not from deposit. If your design needs several rounds of revision, the clock doesn’t start until both sides sign off. Submit clean vector files or give clear feedback quickly to protect your timeline.

Working backwards from your event date

The most reliable way to place a custom medal order is to pick your event date and count back:

Air freight example (DDP)

Milestone Days before event
Event day Day 0
Medals arrive at venue Day 2–3 (allow buffer)
Cargo-ready at factory Day 7–10
Sample approved, production starts Day 21–24
Artwork approved, sample starts Day 28–31
Submit enquiry and deposit Day 35–42

For a 1 December event, work back to a late October deposit and artwork submission.

Sea freight example (DDP)

Milestone Days before event
Event day Day 0
Medals arrive at venue Day 5–7
Cargo-ready at factory Day 30–42
Sample approved Day 44–56
Submit enquiry and deposit Day 56–70

For a 1 March event, sea freight requires a deposit in early January.

Rush orders and what actually works

Factory lead time of 14 days is a firm floor—it is determined by physical processes (mould engraving, stamping, plating, enamel curing) that can’t be compressed below a safe minimum.

What can help if you’re running late:

  1. Use an existing mould. A repeat design skips the mould-making step and can shave 2–3 days.
  2. Simplify the design. Fewer enamel colours and a standard shape process faster than a complex 3D relief with seven colours.
  3. Air freight. Switching from sea to air cuts transit time by 20–30 days, with a corresponding freight cost increase.
  4. Ask about expedite fees. For genuinely tight timelines, contact us directly—we can sometimes prioritise production for an additional charge, but this cannot be guaranteed and depends on the current schedule.

If your event is fewer than three weeks away, air freight and an existing mould are the only realistic levers.

A note on the Chinese New Year shutdown

The annual factory closure around Chinese New Year affects any order placed in the November–January window. In 2027, the holiday falls on 6 February—eleven days earlier than 2026. Production lines slow from mid-January and go offline from late January through mid-February.

If your event is in January or February, treat the deadlines in the table above as the latest possible, not the typical. For more detail on the 2027 shutdown and what it means for medal orders, see our Chinese New Year ordering deadline guide.

Payment and what to prepare for your enquiry

Payment terms are 50% deposit before production, 50% balance before shipment. Sending the deposit and final artwork at the same time keeps things moving fastest.

When you get in touch, have these ready:

  • Quantity and number of designs
  • Event date (or delivery deadline)
  • Medal diameter and thickness (if you have a preference)
  • Plating colour(s) and enamel requirements
  • Ribbon or packaging preferences
  • Destination country (affects freight and any duty considerations)

The more you can share upfront, the faster we can confirm your timeline and issue a quote.


Ready to check whether your timeline works? Get a quote and we’ll confirm sample and production dates based on your event schedule.